Millwrights Place and Coopers Court residential scheme
297 apartments across two buildings on the former Avon Fire and Rescue headquarters site
Project director Dave John explains how Willmott Dixon delivered a defect-free 14-storey high-rise residential development that would be a proving ground for Building Safety Act requirements
When Willmott Dixon took on the challenge of delivering 297 apartments across two schemes in Bristol's city centre, we knew we were entering uncharted territory for us in Bristol. The Millwrights Place and Coopers Court project would become our tallest residential building to date in the region, and a proving ground for the new Building Safety Act requirements that were emerging at the time and reshaping how we build high-rise homes.
The result? A defect-free completion that building control inspectors called "exemplar good practice," earning our project director Dave John a gold medal at the Construction Manager of the Year awards.
While this project did not technically fall under the new Building Safety Act and secondary regulations it was very much on the horizon, we therefore decided to adopt the principles we knew were going to be requirements for the future. Where traditional builds might generate thousands of documents, this project required 35,000 pieces of documentation—including 8,000 photographs and comprehensive quality checks that formed a detailed building file for future reference.
"The vast majority of our 25-person team had never worked on high-rise residential before," explains Dave John, who led the project. "We had to completely rethink our approach to materials, documentation, and team structure."
Key changes included:
Halfway through construction, building control invited the new regional Building Safety Regulators team to visit the site. Their verdict? The project demonstrated best practice in the industry's new regulatory environment.
Building in Bristol's city centre presented logistical challenges that demanded innovative solutions. The site housed three tower cranes, 29 mast climbers, and three goods hoists—all while maintaining 24/7 access to an active fire station next door.
Our solution: We established an off-site storage yard in Yate, North Bristol, near the M4/M5 interchange. This allowed us to secure materials like brick slips, insulation, and cladding components away from the constrained site, calling them in precisely when needed.
"It's an added cost having materials delivered twice," John notes, "but it was money well spent. We could maintain our construction program without compromising the neighbouring fire station's operations."
Learning from previous projects, we revolutionized our approach to balcony installation. Rather than the traditional method of individual steel erection and fitting—which required multiple trades to access finished apartments—we employed prefabricated balcony systems.
The transformation was remarkable: Nine to ten balconies could be installed daily, with balconies manufactured off-site and stored until needed. Beyond one operative guiding them into position, no one needed to enter completed apartments, dramatically reducing remedial work and maintaining quality standards.
For a project of this scale, nearly 300 apartments across 14 stories, traditional management approaches wouldn't suffice. We developed what became known as our "coloured boxes schedule," dividing work into specialized zones with dedicated two-person management teams.
Each "box" represented a specific phase:
This system allowed managers to focus on their specialized area while maintaining clear handover points, ensuring quality and efficiency throughout the vertical construction process.
Quality Through Preparation
Before constructing a single apartment, we established a quality room showcasing every tap, sink, and shower head for customer approval. This led to sample apartments for each scheme—a critical step that ensured all 297 units met exact specifications.
"You wouldn't want to make a mistake 300 times," John emphasises. "The sample apartments were vital for residential work of this scale."
Delivering Results Under Pressure
Despite facing challenges including adjacent development delays, district heating connection postponements, and the complexity of dual end-users (Granger PLC for rental apartments and housing association Abri for affordable homes), the project achieved remarkable outcomes:
The Millwrights Place project has become a blueprint for high-rise residential delivery in the post-Building Safety Act era. Our experience demonstrates that while new regulations require enhanced resources and different approaches, they ultimately deliver better buildings and safer homes.
Key takeaways for future projects:
For developers and housing providers navigating today's regulatory landscape, the project proves that achieving defect-free delivery is possible—but it requires partners who understand both the technical requirements and practical realities of modern construction.